ECRL Project Nears Completion with 92.62% Progress as of February 2026, Reports Amir Hamzah
Kuala lumpur: The East Coast Rail Link (ECRL) project has reached 92.62 per cent completion as of February 2026, aligning with the schedule to finish the Kota Bharu-Gombak alignment by the end of this year and start commercial operations in