KB Sentral Soil Treatment Work Delayed By 21 Days
Kota bharu: The soil treatment work for the Kota Bharu Integrated Bus Station Terminal (KB Sentral) project is now 21 days behind schedule, with actual progress at 40.07 per cent compared to 47.26 per cent according to schedule.